CSMS #13-000395
ACE Development and Deployment Schedule and Stakeholder Backlog Posted on CBP.GOV
· View this week in context on the trade timeline
System UpdateLow urgency
CSMS# 13-000395 - ACE Development and Deployment Schedule and Stakeholder Backlog Posted on CBP.GOV
U.S. Customs and Border Protection sent this bulletin at 08/08/2013 11:46 AM EDT
You are subscribed to Rail Manifest for U.S. Customs and Border Protection. This information has recently been updated, and is now available.
CSMS# 13-000395 - ACE Development and Deployment Schedule and Stakeholder Backlog Posted on CBP.GOV (apps.cbp.gov/csms/csms.asp?srch_argv=13-000395&srchtype=all&opt=1)
08/08/2013 12:43 PM EDT
Rail Manifest
CBP has posted the most current ACE Development & Deployment Schedule and Stakeholder Backlog to cbp.gov for your reference. The deployment schedule is based on the development plans for completing all core trade functionality in ACE within the next 3 years. The plan proposes 7 major deployments over the coming 3 years. The plan now includes the following mandatory dates:
• May 1, 2015: Mandated use of Manifest – All electronic export and import manifest data must be transmitted via ACE.
• November 1, 2015: Mandated use of Cargo Release – All data associated with the release of cargo, including PGA interactions, must be transmitted via ACE.
• October 1, 2016: Mandated use of ACE.
The 3 documents, development schedule, deployment schedule and stakeholder backlog, have been posted to CBP.gov at the link below.
cbp.gov/xp/cgov/trade/automated/modernization/whats_new/
- Programs affected
- ACE, AMS, Cargo Release